This webpage is to inform readers of updates to the website. The updates will remain for a period of three months and then will be replaced with the following month.
Downloadable Readers
| Date |
Title |
Summary |
| January 2012 | ||
| LJK Document | ||
| 1/1/2012 |
Documents Posted in 2011 on SkagitRiverHistory.com | “During 2011 we published 165 historical documents and 125 documents dated in 2011 for a total of 290 documents.” Document lists each posting by jurisdiction of creation divided by pre-2011 & 2011. |
| City of Burlington Documents | ||
| 3/03/2011 |
Reichhardt & Ebe Engineering Plans for Dike District 12 Levee Certification |
The current plans to certify Dike District 12 levees. This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| 8/10/2011 |
Skagit River General Investigation Study Scoping Meeting Comments - City of Burlington |
34 slide presentation to the
the 2011 Skagit River GI Scoping Efforts by the City
of Burlington. Main focus is flood storage. “•With additional Baker flood storage in place (139,000 AF in accordance w/ Baker advance drawdown targets), Skagit peak flow reduction will be 13,000 – 18,000 cubic feet per second. “ – Reduces downstream surface water elevation 1.5 feet “ – Coordination w/ downstream storage (40,000 – 60,000 acre-feet in the Nookachamps basin) reduces another 1.5 feet. “•Similar reductions can occur from Ross storage and operation “• At least 3-4 feet flood reduction in total.” |
| Corps of Engineers Documents | ||
| 6/24/1977 |
Northern Pacific Division (Portland) Headquarters ltr to Seattle District re Skagit River Levees and Channel Improvements |
". . . based on a review of the authorizing document and assuming such extension is justified and desired by local interests, extension of the project that far via a phase 1 report would require a significant Post Authorization Change report requiring Congressional action." . . . An alternative course of action would be to proceed with a GDM report covering the general project area reconsidering the degree of protection to be provided. At the same time preauthorization studies could proceed on the area upstream under the authority of the PSFAW study or under Section 216. Such a procedure would permit early construction capability and at the same time cover the full flood control needs of the area." |
| 7/11/1977 |
Corps ltr to Skagit County Planning re deauthorization of the Avon Bypass
project Document contains attachments: Avon Bypass Information Sheet; Project Deauthorization Review; Basin Map |
'. . . a. Additional Flood Control at Upper Baker Project. The Upper Baker Project recently received congressional approval. The operation of the Upper Baker Dam will be modified for flood control purposes by providing up to 58,000 additional acre-feet of flood control storage by increasing reservoir drawdown in the period 1 November to 15 November of each year. Implementation of the project will not require structural modifications to existing facilities. Coupled with flood plain management, the project will increase flood protection in the Skagit River flood plain below Concrete, Washington, by decreasing peak discharges from those now experienced. . . . b. Levee and Channel Improvements . . . the project involves raising and strengthening existing levees downstream from Burlington and Mount Vernon, Washington, and making minor channel improvements to increase minimum channel capacities. In conjunction with the Upper Baker Project, the levee and channel improvements project, if constructed as authorized, would increase the minimum level of flood protection in areas downstream from Burlington, Washington, from 3 years to an average recurrence interval of 11 years, with 3-foot freeboard. Together with the projects mentioned above, the Avon Bypass Project would increase minimum flood protection from 11 to 59 years for the area downstream from Burlington. ' . . . The county has developed a comprehensive flood control plan for the Skagit Valley, one element of which is the Avon Bypass. However, local cost sharing requirements currently are beyond the means of the county. |
| 7/11/1977 |
Corps Regional Planning Branch Work Request | "Request you proceed with the following: Hydrograph analyses at Sedro Woolley: Develop design quality 25-, 50-, 100-, and 200-year flood hydrographs for Skagit River at Sedro Woolley. These shall represent the present river condition and 74,000 acre feet of flood control storage in Baker-Lake. Hydrologic analysis of interior drainage; Routing, combining and backwater analysis." |
| 7/11/1977 |
Corps Study Manager ltr to local Dike District Commissioner on Fir Island | Corps promises to determine the social economic and environmental effects of each alternative as well as the engineering, design and cost estimates |
| 7/18/1977 |
Letter to Corps Headquarters from Congressman Lloyd Meeds re Sauk River dry dam. | Asked the following questions: 1)How much flood protection would be provided; 2)Will a dry dam on the Sauk be engineeringly sound, economically justified and environmentally safe?; 3) What type of time frame needed for study. |
| 7/22/1977 |
Skagit River Levee and Channel Improvements -- Project Schedule | December 1978 Draft GDM; Final GDM April 1979; June 1980 initiate Construction |
| 7/27/1977 |
Corps MFR re responses to 7/18/1977 letter from Congressman Meeds re "Dry Dam" on Sauk River | A "dry dam" for FC only would be "engineeringly sound." The economic justification has not been determined in any studies and would not be available until after re :on level survey studies. We do not understand the term "environmentally safe" but do believe an "environmentally acceptable" project could be formulated. A detailed study of the Sauk could be completed in 4 years at the cost of $400,000. Checkpoint 1 could be reached in 1-1/2 years at a cost of $150,000. |
| 7/29/1977 |
Outline for Briefing District Engineer on Skagit River Flood Problems | Draft notes on what needed to be done for formal briefing to District Engineer. |
| 8/15/1977 |
Corps Draft Maps of the Avon Bypass | Two sets of maps with different intake locations. |
| 8/17/1977 |
Corps "River Mile" maps | March 1965 maps. |
| 8/23/1977 |
Corps Portland Division Headquarters MFR to Corps Headquarters in Washington DC re Reclassification of Avon Bypass Project | Agreed with Seattle District that Avon Bypass should be reclassified from deferred to active. "... Avon Bypass Project authorized by the 1936 Flood Control Act would be constructed as a part of an overall Skagit Valley flood control plan. The authorized project includes construction of the by-pass in the vicinity of Avon as well as construction of upstream levees in the vicinity of Sedro Woolley. and Burlington." NOTE: As of this date studies needed for project had not yet began. |
| 1/31/2012 |
Congressman Larsen Press Release: Larsen, Skagit County to Army Corps: Commit to Funding the Skagit GI | “The Skagit Valley community is united behind the Skagit G.I. which provides the basis for comprehensive flood control projects. The Skagit G.I. has been progressing for more than fourteen years, funded primarily by Congressional appropriations each eligible year. With a long history of devastating floods, the communities along the river have been looking to construct flood control projects that will increase safety for those living in the Skagit River valley. The Corps itself has recognized how important this G.I. study is. Through the Reset Initiative the Corps gave the Skagit G.I. a much needed higher priority level to bring about its completion in a fiscally responsible manner. An interruption to the forward progress of the study due to a stoppage in funding would be a disservice to the residents of the Skagit Valley. Less than $4 million is needed to complete the investigation. Allowing the Skagit G.I. funding to lapse would waste the $6.5 million of federal funds already invested in addition to the matching funds contributed by the local community. ” |
| FEMA Document | ||
| 1/20/2012 |
FEMA Levee Approach for Public Review Online Forum Presentation | 69-slide presentation on FEMA's plans to map non-accredited levees for the National Flood Insurance Program. The webinar with audio is available from FEMA as well as a Q&A webpage. |
| Puget Sound Energy Documents | ||
| 1/11/2011 |
Tetra Tech Imminent Flood Analysis Article 107 (c) Presentation to the Jan. 11, 2011 meeting of the PSE Aquatic Resources Group Meetng |
55-slide presentation on how preemptive drawdowns of the Baker River reservoirs
would impact flooding. This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| 5/10/2011 |
Draft Meeting Minutes Baker River Project Implementation Aquatic Resources Group Article 107(c) Workshop |
“Settlement Agreement 4.1.1 created the requirement
for PSE to use reasonable best efforts to draw down the reservoirs to target
elevations ahead of an imminent flood event. Article 107(c) calls for PSE to
consult with ARG members, the USACE and Skagit County to develop means and
operational methods to operate the reservoirs in a way that is consistent with
the license. This workshop provides an opportunity to gather input from the
various stakeholders. ... When a water event is approaching, the National
Weather Service generally issues a warning several days in advance. 107(c) is
focused on actions during this time period. At a point when a flood is declared,
the Corps assumes control of the project with PSE’s cooperation. ... “What triggers an imminent flood draw-down? Mark responded that each event is evaluated on a case-by-case basis, depending on weather conditions, forecasts, time of year and reservoir levels, etc. Chal concurred and referenced the “double pumper” event in Oct. 2003 as an example of successful drawdown ahead of a flood.” This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| Skagit County Document | ||
| 7/25/1977 |
SCBCC response to 7/11/1977 ltr from Corps |
"... Skagit County's county-wide flood control zone will be an asset should any large projects, such as the Lower Levee Project or the Avon Bypass Project, be undertaken..." . . . "All of the Diking Districts and the County Engineering Department feel that we should keep working against the deauthorization of the Avon Bypass. |
| Skagit County Flood Control Zone District Advisory Committee Documents | ||
| 1/23/2012 |
Agenda for Monday, January 23, 2010 Meeting |
Meeting will have a Skagit GI Update & a nhc Hydraulic Effectiveness Report presentation. |
| 11/4/2011 |
Handout: Skagit River Flood Risk Management Study Hydraulic Effectiveness of Measures Spreadsheets |
A series of spreadsheets in small print showing the impact in CFS of potential flood projects. |
| 1/12/2012 |
Handout: Skagit River Flood Risk Management Study Hydraulic Effectiveness of Measures FINAL DRAFT |
“This report describes analysis of the hydraulic
effectiveness of various measures proposed for management of floods in the lower
Skagit River basin, focusing on conditions at and downstream from Sedro‐Woolley.
The intent of the work is to identify those measures which hold promise for
improving flood management and for which additional more detailed analysis is
warranted. Hydraulic effectiveness is defined for current purposes as the impact
of the proposed measure on flows and water levels in the Skagit River (including
the North and South Forks) upstream and downstream from the measure location,
and the impact on spill from the river channel onto the floodplain.” See also: nhc Presentation to SC FCZD AC, Re: Skagit River Flood Risk Management General Investigation Hydraulic Effectiveness of Measures |
| 1/12/2012 |
nhc Presentation to SC FCZD AC, Re: Skagit River Flood Risk Management General Investigation Hydraulic Effectiveness of Measures |
33 slide presentation on the Skagit River Flood Risk reduction potential of
measures being reviewed by the Skagit River GI Study. Hydrology is from
the Corps March/April 2011 report. See also: Corps Skagit River Basin Skagit River Flood Risk Management Study Draft Report Hydraulic Technical Documentation, nhc Skagit River Flood Risk Management Study Hydraulic Effectiveness of Measures FINAL DRAFT |
| US Fish & Wildlife Service Document | ||
| 10/10/2000 |
Letter to District Engineer, Corps of Engineers Seattle District - Re: Planning Aid Letter; Skagit River Flood Feasibility Study |
“Levees have channelized the river and isolated the flood
plain, nearly eliminating flood plain storage of water, sediments, and
nutrients. The loss of flood plain function has exacerbated flood problems and
disrupted ecological functioning. By precluding lateral movement of flood
waters, levees reduce groundwater recharge, important for retaining a natural
range of variability of flows to which salmon have adapted. Routing of nutrients
is also disrupted. “Of all the structural measures discussed as part of the Skagit River Flood Feasibility Study, we believe that setback levees hold the most promise for restoring natural processes in the Skagit. Setback levees would increase the river 5 connectivity with its flood plain and would allow more room for water storage and conveyance in high flow events. Loss of flood plain storage has worsened flooding and habitat for fish, so it makes sense to reverse that process by pulling back the levees.” This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| Washington State Department of Ecology Document | ||
| 12/30/2011 |
Letter to County Commissioners, Re: Skagit River Basin Instream Flow Rule |
“Thank you for your follow-up letter of December 7, 2011, regarding the Skagit
Instream Flow Rule. I am pleased to hear that we have a mutual commitment to
finding solutions to the water supply problems in the Nookachamps and
Fisher/Carpenter Sub-basins of the Skagit Watershed. As you point out in your
letter, we also recognize the difficulties presented by
the ongoing lawsuit brought by the Swinomish Tribe.” See also: 11/15/2011 Letter to Governor Gregoire, Re: Skagit lnstream Flow Rule, 11/28/2011 County Commissioners Letter to Governor Gregoire, Re: Water Rights in the Skagit River Basin, 12/7/2011 Letter to State Department of Ecology Director, Re: Director Letter of Dec. 6, 2011 |
| General Webpage Updates for January 2011 | ||
| Issues Page | New documents posted to Avon Bypass, Baker Dams, FEMA FIRM Appeal Issues, Fish Issues, Hydrology, Ross Dam & Sauk River Dam | |
| Quote of the Month | "A levee may not always eliminate the misery"... | |
| Rain Gauge |
Updating to conclude 2011. |
|
| December 2011 | ||
| City of Burlington Documents | ||
| 6/1/2011 | Update on Flood Control Provisions, with Emphasis on License Article 107(c) From the Perspective of the Local Communities |
55-slide presentation submitted to FERC in D.C. Slides 39-45 explain how
drawdown would work with the Baker River Dams in the event of an imminent flood. This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| 7/28/2011 | Letter with City of Burlington, City of Mt. Vernon, City of Sedro-Woolley & Town of La Conner to Skagit County Government, Re: Review Comments, Puget Sound Energy's Preliminary Draft Report, "Reservoir Management Related to Imminent Flood Conditions" |
"Flood control is a federally authorized purpose of the Baker Hydroelectric
Project. However, hydrologic analyses performed by the Corps of Engineers and
Skagit County indicate the existing authorized 74,000 acre-feet of flood storage
is not adequate to capture the basin's own 100-year event. About 140,000
acre-feet of flood storage is necessary for that. Therefore, in a medium-tolarge
flood event, the Project will be forced to discharge water into the Skagit River
peak flow, thereby increasing flood damage. License article 107(c) provides a
mechanism for providing the additional necessary flood storage only when it is
needed - in the event that a large Skagit River basin flood is imminent- in a
way that also can be expected to protect aquatic resources." This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| Corps of Engineers Documents | ||
| 3/1965 | COE Skagit River Flood Control Report |
100 yr flood at Sedro Woolley 239,000 cfs. . . . The existing levee system rests on a foundation of silts and sands common to the delta area. Differential heads of water in flood flow periods result in seepage through levee embankment and levee foundations, causing boils and blowouts that flood adjacent croplands. . . . The semi-pervious foundation conditions preclude any general raising of levees without extensive broadening of the levee sections, construction of cutoffs to reduce seepage and relocation of the road systems adjacent to the levee system. . . . Widening the Skagit River to carry flood flows is also infeasible. To achieve the same results as the Bypass and levee and channel improvements would produce, the channel would have to be widened from 300 to 600 feet from the downstream limits of Sedro Woolley to the mouth of the river, a distance of over 20 miles. . . . The possibility of substantially increasing existing levee heights was opposed by the City Engineer of Mount Vernon and representatives of diking districts because of the hazard of underseepage and blowouts through porous foundation materials. . . . Representatives of the Washington State Department of Game and the U. S. Fish and Wildlife Service stated that the proposed levee and channel improvements would not adversely affect the runs of anadromous fish in the Skagit River, . . . The Avon Bypass project for flood control was endorsed by the Washington State Departments of Conservation, and Commerce and Economic Development, the Skagit County Board of Commissioners, the Skagit County Flood Control Council, the City Engineer of Mount Vernon, and local residents. The Chairman of the Skagit County Board of Commissioners stated that the people and taxpayers of Skagit County could be assured that they would have the right to vote on funding of local cooperation requirements for the project. . . . Opposition to the Bypass project was expressed by representatives of Fire District No. 6 and Diking District No. 12 on the grounds that the Bypass cost would be excessive and would sever both districts and make access difficult. A petition signed by 740 persons was presented by a citizens' group that opposed the Bypass and any plans to modify the Bypass for other purposes. |
| 3/1975 |
Public Brochure re Additional Flood Control at Upper Baker Project Dept. Ecol. = State Department of Ecology EPA = Environmental Protection Agency PNWWA = Pacific Northwest Waterways Association SWCD = Soil & Water Conservation District Sierra = Sierra Club |
A comprehensive plan, completed in 1971, called for increasing Skagit River
flood control through use of reservoir capacity provided by Puget Sound Power
and Light Company's Upper Baker hydroelectric power project in addition to the
16,000 acre-feet of storage space now available during the winter flood season.
The detailed feasibility investigation being completed by the Corps of Engineers
was in follow-up to the comprehensive study and undertaken under the same
authority. . . .
Land use zoning,
development restrictions, flood proofing and early flood warning are flood plain
management elements of this alternative which would be continued by
Skagit County and the State of Washington.
. . . Baker Lake
would be lowered to provide a total of 74,000 acre-feet of flood control storage
between 15 November and 1 March each year.
. . . Although
increased flood control
capability has the potential of creating increased development pressure on flood
plain lands, especially those close to urban areas and those now
protected by dikes and levees,
this pressure is
expected to be minimal. . . .
However, the application
of stringent flood plain management techniques and flood plain zoning by Skagit
County, as called for in the recommended plan, should reduce the
likelihood and severity of such losses.
. . . The U.S. Fish and Wildlife Service and the National Marine
Fisheries Service late in the study asked that flood control drawdown
occur earlier than
necessary for flood control in order to benefit Baker Lake salmon production.
This earlier drawdown would increase power losses and, therefore, would
have to be justified by fishery enhancement benefits. No current provision
exists in the FPC license for such a project operation change.
Because of this
and the lack of data on fish production, the Corps study did not evaluate the
early drawdown proposal. . .
.
Detailed
engineering, economic and environmental impact studies were conducted over the
past 2 years . . .
Land use. The
increased flood protection provided by this alternative (additional
58,000 ac ft storage) would not be sufficient to allow relaxation of
current restrictions on intensive developments in flood hazard areas.
Therefore,
no effect on land use is expected.
False
sense of security. Encourages development of flood plain for uses
incompatible with flooding. (Sierra)
Would create a false sense of security |
| 9/29/1976 | USACE Work Request for Wilderness Village (Concrete) | Dept of Ecology wanted Corps to re-evaluate water surface profiles based on highwater data recently recovered by the developer. Developer had written affidavits from residents in the area who witnessed high water in 1909. |
| 10/15/1976 | ACOE MFR RE Levee and Channel Improvements | "...authorized in 1966" . . . "includes the following elements: (a) raising low spots on riverbank levees to provide a minimum of 2 feet of freeboard, (b) -increasing top widths to a minimum of 10 feet, (c) flattening overly steep Side slopes to a maximum of 1 vertical to 2 horizontal, (d) - the-addition of riprap at critical locations, and (e) channel widening 'improvements at three locations to remove obstructions to flood flows." . . . " Providing a minimum of 100-year protection for urban areas will be considered with a possibility of higher protection provided by Upper Baker storage or other measures ." |
| 1/14/1977 | Draft letters to the President from Dept. of Agriculture and the ACOE |
The documents represent what happens when there are one too many agencies
trying to comment on a flood project when one of the agencies doesn't know
anything about the flood issue. The Dept. of Ag stated, "In addition, the Department of the Army, in their
response to the study report, pointed out
that designation of the
Sauk River would preclude construction of, a flood control storage project on
the river. However,
alternatives to the Sauk
River site exist which would provide the same degree of flood protection for
downstream areas. |
| 1/27/1977 | ACOE MFR RE telephonic conversation with Commissioner Jerry Mansfield re funding for the flood control project | Project Manager advised Commissioner Mansfield to have local interest write their Congressmen and Senators to show a "continued interest" in the project. He suggested writing separate letters to each representative. |
| 1/27/1977 | ACOE MFR re telephonic meeting with Commissioner Norris | One of Commissioner Norris's first official acts after having just been elected was to contact the ACOE and he noted, "that flood control for the Skagit River is one of his primary interests..." Throughout the years and especially during his term as Mayor of Mt. Vernon Bud Norris remained true to his primary interests. |
| 2/23/1977 | ACOE DF ("Disposition form") re meeting to review the hydrology and hydraulics information available and the needs of flood plain and flood control studies |
"During the discussion ... three things became clear. (1)
Existing data is not sufficient. (2) Data needed
for the flood plain study is different data than needed for the flood control
study; (3) difference of opinions exist regarding the needs for the flood
control study. "Lack of capability to perform timely hydrology studies should not place limits on extent of flood protection considered and study schedule should be established to agree with District priorities and capabilities. An early meeting should be scheduled with Chief, Engineering Division to consider any needed reordering of priorities or delays of study." |
| 4/13/1977 | ACOE MFR re: status of Skagit River Levee & Channel Improvement Study | Although the hydrology study had not started yet there was no need to seek additional funds "(beyond existing $100,000)". |
| 4/13/1977 | Ltr to County Commissioner Howard Miller fm ACOE re Skagit County Flood Insurance Study be expedited | Results of Skagit River study scheduled to be completed July 1, 1978. The entire study of the basin scheduled for completion in September 1979. |
| 5/6/1977 | ACOE District Engineer ltr to Portland District Headquarters re: scope and design for the Levees and Channel Improvement Project reformulation | ". . . primary concern of the Levees and Channel Improvement Project should be urban flood damage reduction for Mount Vernon, Burlington and Sedro Woolley areas . . . " . . . During the last decade, conditions in . -the area have changed considerably and the scope and level of flood damage reduction should be reevaluated " . . . "In order to accommodate this need for considering a higher level of flood protection for the urban areas, more extensive surveys, foundation investigations, hydrology, hydraulic and economic studies will be required than were previously anticipated." |
| 5/9/1977 | ACOE MFR re: Avon Bypass Deauthorization - Meeting with Skagit County Engineer | We told Mr. Johnson that we would be sending out a letter alerting local officials to the deauthorization study. We told Mr. Johnson that the first element of work which we would be getting underway would be a survey contract to map the existing levees and provide topography for use in our hydrologic and hydraulic studies. NOTE: This strongly suggest that the entire $4 million dollar GDM was done in two years. |
| 5/19/1977 | ACOE ltr to local resident of Skagit Valley re: information he requested | "We have completed most of our field surveys and foundation exploration and are currently developing the hydrologic model to determine the exact extent of the 100- and 10-year flood plain. As stated in the public brochure, the alternative cost estimates were not based on detailed studies, but were preliminary engineering estimates of the range of casts that could be involved for each of the alternatives." |
| 5/19/1977 | ACOE MFR re: Skagit County Flood Insurance Study | Work list for study. "They plan (GDM Study) to do the kind of analysis of delta flooding that we rejected for the Skagit County FIS because it would cost over $100K. If their plans gel, we could ask FIA if they want us to include the analysis in the FIS. We hadn't planned to re-study the delta for the FIS. " |
| 6/8/1977 | ACOE DF re: All Hands Meeting to agree on the "plan of study" for the 1979 Levee and Channel Improvements Study. | ". . .no significant problems are known at this time." . . . ". . .during the last decade, urbanization has increased considerably and the scope and level of flood damage reduction should be reevaluated for the urban areas." NOTE: This is an amazing document that shows us that as of June 8, 1977 the GDM had not been started, yet it was published in 1979. |
| 6/15/1977 | ACOE MFR re: Meeting to agree on the "plan of study" for the 1979 Levee and Channel Improvements Study which took place on June 13, 1977 | " . . . of the $28,000 listed for report preparation,$6,000 would be used by Drafting Section to prepare the final plates " . . . "Regional Planning Section in coordination with Civil Design Section will start work on design in April 1978 and complete in September 1978." . . . " After the design is completed about: 3 months will be required to prepare the draft General Design Memorandum and another six months to complete the final GDM for submittal to NPD. The schedule for submittal of the Draft GDM would be December 1978 and for the final GDM May 1979." |
| 6/24/1977 | ACOE Headquarters in Portland ltr to Seattle District Engineer re: extending Levee project upstream through Mt. Vernon and Burlington | ". . .Assuming the Avon Bypass is not deauthorized, your report must include a "last added" analysis of each element of the overall protection plan of the basin. Your proposal to extend the study scope upstream through the areas of Mount Vernon, Burlington and Sedro Woolley does create a separate set of problems ". . . ". . . extension of the. project that far via a phase 1 report would require a significant Post Authorization Change report requiring Congressional action." |
| Corps of Engineers GI Study Scoping Document | ||
| 8/10/2011 | Dike District 17 Submission to US Army Corps of Engineers 2011 Scoping Efforts | "Burlington Levy Certification program... We must take as much of our critical infrastructure out of harms way with the least amount of impact to the environment. Water running through the city and then back to the river or the sound ... not good." |
| Puget Sound Energy Documents | ||
| 10/13/2009 | R2 Resource Consultants Presentation: Environmental Effects of High Water Events Middle Skagit River, Washington |
11-slide presentation reviewing the impacts of floods on Chinook salmon
survival. May want to see slide 9 where years following recent major flood
events have direct correlation to lack of young salmon survival in the Skagit. This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| 5/26/2011 | License Articles applicable to Article 107 c or Flooding | All legal language and tables governing flood control storage management for Upper Baker Dam & Lower Baker Dam. |
| 7/11/2011 | PSE Publication of FERC License to Operate Baker River Hydrologic Project Settlement Agreement Article 107 |
“Licensee shall consult with the ARG, and specifically Skagit County and the
Corps of Engineers, to develop means and operational methods to operate the
Project reservoirs in a manner addressing imminent flood events and consistent
with the requirements of the license. Appropriate means and methods may include,
without limitation, additional reservoir drawdown below the maximum established
flood pool. Licensee shall submit a report to the Commission within three years
following license issuance describing any operational changes developed as a
result of this consultation.” Red print Puget Sound Energy's. This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| Skagit County Documents | ||
| 2/3/1977 | Article in the Skagit Valley Herald re "Skagit flood dispute halts permits". | This article deals with permits in Wilderness Village, 3 miles downstream of Concrete. See (9/29/1976 USACE Work Request for Wilderness Village (Concrete)) County placed a moratorium on issuing permits from Sedro-Woolley upriver in the floodplain. |
| 3/1/1977 |
Ltr to ACOE fm Skagit County Commissioner Howard Miller re request for flood study to be expedited |
“Understanding that the final flood insurance study may indicate substantial changes with the information available today, it is our request that this study be expedited as much as possible so that the possible impact on those properties that may not eventually be affected by the floodway can be reduced.” |
| 6/15/2010 | nhc Memorandum: Skagit River Gl Study- Seasonality Assessment of Flood Storage |
“Hydrologic analyses of existing condition regulated flows conducted to date
have ignored the seasonal variation of flood control storage and have assumed
that the required maximum amount of storage (74,000 ac-ft at Upper Baker and
120,000 ac-ft at Ross) is available for all floods, regardless of the date of
occurrence. The full amount of flood storage is not required at Upper Baker
until November 15 and at Ross until December 1. The purpose of the work
described in this memo was to assess the impact of lower flood control storage
requirements prior to December 1 on regulated peak flows on the Skagit River
near Concrete (i .e. downstream from the Baker River confluence). ... “Operations at Upper Baker have also deviated from expected future operations since 2004. In accordance with the requirements of a relicensing agreement, an Interim Protection Plan (IPP) was introduced in 2004 to improve fish habitat in the Baker River by reducing rapid fluctuations in flow. Under IPP-related project operations, more storage than required would be available in the Baker River project early in the flood control season. ... “A further change affecting flood control performance has been the implementation by PSE since about 2006 of flood control pool buffers at both Upper Baker and Lower Baker. The buffers provide additional storage above that required for flood control operations per the operating license. At Upper Baker, this additional storage is 26,000 acre-ft, so that the bottom of the buffer is approximately 7ft below the maximum permissible pool elevation in the flood control season. At Lower Baker, the bottom of the buffer is approximately 5 ft below the spillway crest elevation, representing approximately 9,850 acre-ft of storage below the spillway crest. The purpose of the buffers is to provide PSE with operational flexibility while avoiding, to the extent possible, incursion into the formal flood control storage space at Upper Baker. PSE operates the reservoirs to try to maintain water levels toward the low end of these buffers (water levels are generally maintained 2 to 3 feet above the bottom of the buffer), however there is no formal operating policy for the buffers. ... “The Baker Project WCM should be updated to show flood control storage requirements per the current FERC license. Future updates to the WCM should be anticipated and coordinated with PSE to reflect operational changes adopted as a result of future implementation of new FERC license conditions. ” This document was submitted to the 2011 Skagit River GI Scoping Efforts by the City of Burlington. |
| 11/21/2011 | County Commissioners Letter to Swinomish Indian Tribal Community, RE: Skagit Instream Flow Rule |
“We respect that your expression of tribal sovereignty involves vigorous
advocacy for salmon, and there is little question Swinomish has become a force
in the salmon habitat restoration industry. Yet Swinomish is a significant
participant ¡n Skagit County's economy and community in many other ways, which
deserves due consideration when contemplating major environmental litigation
involving the land and homes of thousands of Skagit County citizens.
Nearly two decades of litigation over salmon habitat has
accomplished very little for salmon, has wasted millions on legal fees that
could have otherwise been used for on-the-ground habitat restoration and other
constituent needs, and, perhaps most unfortunate, has perpetrated a cycle of
animosity in our community.” See also: 11/17/2001 Letter to Governor Chris Gregoire, Re: Skagit County Government Letter on Skagit Instream Flow Rule |
| 11/28/2011 | County Commissioners Letter to Governor Gregoire, Re: Water Rights in the Skagit River Basin |
County responds to the Swinomish "Liar, Liar pants on fire" letter.
“At this point, as nearly as we can ascertain, the
reason for the continued controversy arises from the desire to create new
judicial precedent limiting the scope of Ecology's power to establish exempt
well reservations, something mostly relevant to other river basins besides
Skagit. ... Extensive litigation capability
frequently drives its own employment in search of a justification for the
expense involved. While we comprehend why Swinomish staff continues to
vigorously advocate for more litigation over the Skagit Instream Flow Rule in
close conjunction with CELP, we strongly believe that effort is against the
interests of both Skagit Basin salmon stocks and our community, including the
members of the Swinomish Indian Tribal Community.” See also: 11/15/2011 Letter to Governor Gregoire, Re: Skagit lnstream Flow Rule, 11/17/2011 Letter to Governor Chris Gregoire, Re: Skagit County Government Letter on Skagit Instream Flow Rule, 11/21/2011 County Commissioners Letter to Swinomish Indian Tribal Community, RE: Skagit Instream Flow Rule |
| 12/7/2011 | Letter to State Department of Ecology Director, Re: Director Letter of Dec. 6, 2011 |
“Skagit County is more than willing to cooperate and
fulfill our obligations under the law and our agreement with Ecology, and there
is no evidence we have done otherwise. As we have repeatedly communicated
to the Governor in recent days, Skagit County is not asking for a larger exempt
well allocation. Moreover, Skagit County has and will continue to ascertain
whether permit applicants possess a lawful water source, as required by the
Kittitas decision. Since we already have the most restrictive scheme in
place in the Skagit Basin and no other Skagit treaty tribe supports Swinomish on
this issue, we view the threat of treaty rights adjudication as unnecessary. We
fully support the list of solutions identified on page 3 of your letter, but
these put the cart before the horse. Pervasive
litigation by Swinomish attacking nearly every aspect of the basin reservation
system - as opposed to any shortcoming on the County's part - explains the
problems over which your December 6 letter expresses concern.” See also: 11/15/2011 Letter to Governor Gregoire, Re: Skagit lnstream Flow Rule, 11/17/2011 Letter to Governor Chris Gregoire, Re: Skagit County Government Letter on Skagit Instream Flow Rule, 11/21/2011 County Commissioners Letter to Swinomish Indian Tribal Community, RE: Skagit Instream Flow Rule, 11/28/2011 County Commissioners Letter to Governor Gregoire, Re: Water Rights in the Skagit River Basin, 12.6/2011 Letter to County Commissioners, Re: Skagit River Basin Instream Flow Rule |
| Swinomish Tribal Document | ||
| 8/10/2011 | Swinomish "Possible Environmental Effects for Potential Measures" of Any Flood Risk Reduction Projects |
“...improvements to levees will increase the amount of rock in the river, remove
vegetation, and probably increase bed scour due to the transfer of energy from
the rock faces.” See also: Corps of Engineers 2011 Scoping Efforts, 9/7/2011 Swinomish Tribal Community Ltr to Corps of Engineers Re: Skagit General Investigation Scoping Comments |
| US Fish and Wildlife Service Document | ||
| 3/11/1977 | Planning Aid Letter to ACOE fm US Fish and Wildlife Service re proposed channel and levee improvement project | "This letter reflects our current thinking on these proposed improvements. Our 1974 (sic 1964) report indicated the channel and levee improvements . . would have little effect on fish and fishing. . . . Effects on wildlife were also predicted to be minimal." "However, . . .we believe several very positive features may be incorporated in the project including: Fencing to prevent cattle grazing on top and riverward levee slopes. Reseeding and cleanup of trash and debris along inner levee slopes to facilitate unrestricted passage of flood water..." |
| Washington State Department of Ecology Document | ||
| 12/6/2011 | Letter to County Commissioners, Re: Skagit River Basin Instream Flow Rule |
“Regarding our shared commitment to exercise our respective regulatory
authorities in a coordinated and complimentary fashion,
I am very concerned about recent public information materials from the County.
These materials have asserted that the County does not have any role in water
resources management. This is clearly not the case, as the Washington
Supreme Court ruled recently in Kittitas County v. Eastern Washington Growth
Management Hearings Board. In fact, according to the Supreme Court,
counties have a very important role in water management.
The court held that in making a land-use decision, it is the local
government-and not Ecology-that is responsible for making the decision on water
adequacy as part of its land-use decision. However, the court recognizes that
Ecology should endeavor to provide assistance to counties in making such
land-use decisions, as needed, to ensure adequate protection of water resources.
It is critically important that we find a way to move this conversation forward
in a coordinated and complimentary fashion.” See also: 11/15/2011 Letter to Governor Gregoire, Re: Skagit lnstream Flow Rule, 11/28/2011 County Commissioners Letter to Governor Gregoire, Re: Water Rights in the Skagit River Basin, 12/7/2011 Letter to State Department of Ecology Director, Re: Director Letter of Dec. 6, 2011 |
| Guest Documents | ||
| 12/8/2011 | Property Casualty 360° - Senate Passes Another Short-Term NFIP Extension as Deadline Nears | “The Senate last night unanimously passed legislation extending the National Flood Insurance Program until May 31, 2012. ... “Our priority is preventing another NFIP lapse,” says Tom Litjen vice president of federal government relations for the Property Casualty Insurers Association of America. “More than 5.6 million home and business owners across the country rely on flood insurance, in every state. This is not just a coastal concern.” Tom Santos, vice president for federal affairs at the American Insurance Association, says, “The six month extension...should allow Congress enough time to consider and pass a long-term extension with meaningful reforms that aim to strengthen the program. Necessary reforms include movement toward risk-based premiums and reduced price subsidies.” |
| 12/9/2011 | Property Casualty 360° - Long-Term NFIP Extension Finds Its Way Into Budget/Tax Cut Bill | “Legislation that packages the House version of a five-year National Flood Insurance Program extension into a deal that would extend expiring tax cuts is headed for House floor action and likely approval. The deal would essentially include an NFIP extension in House Republicans’ demands for budget cuts in exchange for their support on extending expiring tax cuts. ... However, one industry lobbyist questions the math involved in saying passing the NFIP reauthorization would save $4.5 billion over 10 years when the program currently owes the Treasury almost $18 billion due to losses created by paying claims from Hurricanes Katrina and Rita in 2005.” |
| 12/21/2011 | The Seattle Times: Battle escalates over building in flood plains | “More than a decade after government biologists
first warned the Federal Emergency Management Agency (FEMA) that allowing
development in flood plains is helping kill salmon and orcas,
environmental groups on Wednesday turned to their
most potent — and controversial — weapon: They asked a
federal judge in Seattle for an emergency injunction that would effectively halt
a sizable chunk of the building in flood-prone areas until FEMA finds a way to
make sure it won't harm endangered fish or whales. “...While it's impossible to know how much construction might be curtailed, the National Wildlife Federation says its review of FEMA data suggests 700 to 800 new structures have been built in flood plains in the three years since the biologists said the practice must change. "Salmon are going over the edge, and we've waited years for it to change and it hasn't," said Jan Hasselman, an attorney with the environmental legal firm Earthjustice, which filed the motion in federal court. "As far as we can tell, not one project has been prevented, delayed, reconfigured or reconsidered" since 2008.” |
| General Webpage Updates for December 2011 | ||
| Historical Quote of the Month | Baker River dam storage and fish runs... | |
| Issues Page | New documents posted this month to Avon Bypass, Baker Dams, Fish Issues, Hydrology & Ross Dam | |
| Photo Gallery | Pictures of the conclusion of levee repairs along the 3-Bridge Corridor between Mt. Vernon & Burlington, WA. | |
| Rain Gauge |
Updating for November 2011. |
|
| November 2011 | ||
| LJK Document | ||
| 11/26/2011 | www.SkagitRiverHistory.com Comments on October 2011 Corps Scoping Summary Report | Comments about various measures proposed in the 10/2011 Skagit River General Investigation Study Scoping Summary Report for the Draft Feasibility Study And Environmental Impact Statement. |
| Corps of Engineers Documents | ||
| 2/3/1961 | USACE Seattle District Plan of Survey Skagit River Flood Control Study |
With regulation at Ross and Upper Baker Dams, a 150,000 cfs flow at SW has a
frequency of about 25 years. ... Flows of 210,000 cfs at
SW have frequencies of about 200 years under existing conditions.
(NOTE: REMEMBER THIS IS BEFORE ADDITIONAL STORAGE BEHIND UPPER BAKER.) ...
damages from flows of this magnitude would total about
$6,600,000. ... objective of this study is to find the most
economically feasible solutions. See also: Public Hearing on Flood Control for the Skagit River Basin, 8 February 1961 |
| 1/18/1963 | Feasibility Report, Skagit River, Washington (Navigation) |
NOTE TO REVIEWER: This is a very poor
copy of the original and very difficult to read. It helps to
enlarge it to 125-150%. This document looked at the history
of a navigation project between Mt. Vernon and Concrete originally authorized by
Congress on May 13, 1947. The final results are in this
report as well as a lot of statistical history on logging and local businesses. "Tug operators advised that a 100-ft channel width and a 6
foot depth would be sufficient for foreseeable navigation requirements." (¶13)
... Approx 1,520,000 CY of material would be dredged. (¶15 & 21)
Estimated that annual maintenance dredging would consist of 380,000 CY.
(¶22b) Two mills at SW sell annually, an
average of 10,500,000 board-feet of lumber to the US Army. (¶27)
Total annual benefits of barge canal would be $592,000. (¶28)
Annual cost $474,000. (¶29) Amt needed to complete
study $45,000. (¶30) The Skagit River navigation study has
been authorized and intermittently underway since 1947 In view of this fact ...
an effort should be made to complete the study as soon as practicable.
... $15,000 needed to complete the study be allocated early in fiscal
year 1964. (¶31) |
| 1/7/1976 | MFR RE Skagit River Flood Fight for Dec 26 1975 high water | River was predicted to reach 29 feet on Dec 27 and locals were concerned about the breaks in the levees on Cockreham levee. Corps "plugged" five breaks in the levees at an estimated cost of $12,000. |
| 4/1/1976 | Handwritten note by Corps Staff re one of the first strategy sessions for the 1979 project. | "New survey report but do under GDM outcome -- solution to problem. . . . Finish in 78 . . . Can't rule out non-structural" |
| 4/22/1976 | Corps DF re Environmental Assessment of Levee Repairs After 1975 Flood Event | Repairs took place on Cockreham Island. Skagit floods "characterized by sharp rises of relatively short duration from October through March." . . . "The Skagit River system produces more runoff than any other river basin in the Puget Sound area." 100 year flood 266,000 cfs. 50-year flood 224,000 cfs. Zero damage 60,000 cfs. Present levee system with 2ft of freeboard 84,000 to 130,000 cfs or 3 to 11 year protection. . . . Ross Dam controls about 30 percent of the basin's runoff with 120,000 acre-ft of storage space. . . . During the 1972-1973 collection period, nearly 14,400 salmon were captured, trucked, and released into Baker Lake and adjoining artificial spawning beaches . They consisted of 10,000 sockeye , 4, 000 coho, 250 chinook , and 30 chum. In addition, 50 steelhead trout were captured and released. . . . The damaged areas at the town of Hamilton, and the four damaged portions between Hamilton and Lyman occurred where the high water flow was either restricted or at a sharp change in direction without adequate floodway area to handle the resulting turbulence. The floodwater was most destructive where the levee was breached; in some of these cases the water velocity cut a channel from the river through the vegetated bench and beyond into the agricultural area. . . . The greatest loss to fish will be the loss of eggs placed in the gravels by spawning fish prior to the flood. |
| 6/23/1976 | Corp MFR re Skagit County Flood Insurance Study -- Corps Projects | “. . .levee work was authorized via a 1965 report on the Skagit River, with the proviso that upstream storage is provided first. Now that the Baker Lake storage project is authorized, the levee project will be revived.” |
| 6/23/1976 | Corp MFR re Skagit County Flood Insurance Study -- Delta Flooding | "Lloyd Johnson agreed, with the exception that he would like to see a more "realistic water surface profile, i.e., "a waterfall", where the floodwaters emerge through the dike area rather than a gradual drop as we had shown in our 1973 report." |
| 3/2011 | Skagit River Basin Skagit River Flood Risk Management Study Draft Report Hydraulic Technical Documentation |
“This report documents the work conducted for the Skagit River Flood Risk
Management Feasibility Study to develop hydraulic computer models and to
establish existing without project hydraulic conditions. . . . The
emphasis in this report is on hydraulic modeling for the lower Skagit River
downstream from Sedro-Woolley. The damage reaches that are evaluated start at
Sedro-Woolley and extend down to the mouth at Skagit Bay. . . .
Revisions to the hydraulic models used for the Flood Risk Management Study and
preparation of the present 2011 update to the Hydraulic Technical Documentation
were carried out by Northwest Hydraulic Consultants Inc. (NHC) under contract to
the local sponsor, Skagit County (contract C20080424, Task Assignment 4,
authorized 15 October 2009).” Report also discusses impacts of bridge debris, potential levee breaches and hydraulic model calibration & validation. Page 37 of this report (page 41 of the PDF) is devoted to debris loads at the BNSF RR Bridge. |
| 4/15/2011 | Flooding in Western Washington: The Connection to Atmospheric Rivers |
“This study utilizes multiple decades of daily streamflow data gathered in four
major watersheds in western Washington to determine the meteorological
conditions most likely to cause flooding in those watersheds. ... The flooding
on the four watersheds occurred during the landfall of ARs [Atmospheric Rivers]
within the warm sectors of extratropical cyclones that were accompanied by warm
advection, lower-tropospheric temperatures 4-6°C above normal, strong low-level
water vapor fluxes from over the Pacific, and low-level moist-neutral stability.
The enhanced onshore vapor fluxes and weak static stability provided a favorable
environment for orographic precipitation enhancement across the region’s steep
terrain. More generally, all peak daily flows that
exceeded a 5-year return period on non-consecutive days in each of the four
basins of interest between WY1980-2009 were associated with landfalling ARs.” One of those basins of interest was the Sauk River. |
| Corps of Engineers GI Study Scoping Document | ||
| 10/2011 | Skagit River General Investigation Study Scoping Summary Report for the Draft Feasibility Study And Environmental Impact Statement |
“The U.S. Army Corps of Engineers, Seattle District (USACE), in cooperation with
Skagit County, is preparing a Draft Environmental Impact Statement (DEIS) under
the National Environmental Policy Act (NEPA) for a proposed flood-risk
management General Investigation (GI) Study for the Skagit River Basin from Ross
Lake to the river mouth at Skagit Bay. This study was requested by Skagit County
because of the potential for significant flooding on the Skagit River. “An initial notice of intent (NOI) for this project was originally published in the Federal Register on November 20, 1997, for a Skagit River Flood Damage Reduction Study (62 FR 62019). Since the original NOI was issued in 1997, the study has evolved to meet new challenges and include ecosystem considerations associated with Puget Sound Chinook salmon and bull trout species listed as threatened under the Endangered Species Act (ESA). On July 29, 2011, an additional NOI was published, recommencing the scoping process (76 FR 45543) (see Appendix A). The purpose of this most recent NOI was to provide opportunity for additional public input and ensure that the study still accurately reflects stakeholder resource issues and concerns.” See also: 11/26/2011 www.SkagitRiverHistory.com Comments on October 2011 Corps Scoping Summary Report |
| Corps of Engineers Public Hearing Transcripts | ||
| 2/8/1961 | Missing Exhibits to Public Hearing Transcript |
This is a series of letters that were submitted during the 2/8/61 Public
Hearing.
Dike 12:
"The dike has
been raised an overall height of 2 feet for a distance of approx. 9 miles.
As they continue
to build restrictions into the river below us, narrowing the stream flow, it
will be necessary to raise the height of the dike."
La Conner:
"In 1882, six
feet of flood water inundated the land, damaged crops, and broke the
dikes.
In 1886 the
Skagit River overflowed and froze and in
1887 a late
spring freshet damaged crops."
Dike 17:
District formed in 1907.
Letter identifies where
the levee broke in 1917 & 1921. Raised
their levee 18 inches above the 1951 level.
Dike 20:
(Nookachamps) Dike not high enough to keep out water over 24 feet.
Dwelly:
Supported dredging for commerce but very opposed to Faber Dam.
WSDOF:
Skagit "most
valuable" tributary to Puget Sound in sustaining commercial sport fishing.
65% of the Chinook salmon spawning area is located on main stem of the
Skagit and tributaries above proposed Faber dam site.
Supported building of Avon Bypass.
Dairy Farmers: "They know what
has happened to them in past floods..."
Many dairy cows died in the 1951 flood.
Mt. Vernon:
Estimated over 4 million dollars of property in harm's way.
Figure included 600 homes and 1,400,000 sq. ft. of commercial property
and 10 miles of sewer lines in flood area.
Total damages
est. $6,200,000.
Burlington:
No loss since 1950. Made no
specific recommendation for a flood control project.
Needed to educate voters on flooding issue. See also: Public Hearing on Flood Control for the Skagit River Basin, 8 February 1961 |
| 8/10/2011 | Reporter's Transcript of Proceedings Skagit County Flood Study Meeting | “NEPA really does encourage citizen participation via public hearings, scoping meetings, these comment periods where you can send in your written comments. Public involvement is a very important aspect of the NEPA process. It's an opportunity for the public to participate in a federal decision-making process and direct an agency's attention to the community's concerns.” |
| Seattle City Light Document | ||
| 9/8/2011 | Seattle City Light Comments on Skagit River General Investigation Study |
“Your NOI formally begins the scoping process under NEPA. As part of the scoping
process, Seattle City Light wishes to comment on the scope of the DEIS. Our
ongoing interest in the GI study stems from our ownership and operation of the
Skagit Hydroelectric Project located in the upper watershed. . . . As we
understand it, the primary intent of the flood risk management feasibility study
is to formulate, evaluate, and screen potential solutions to flooding problems
within the basin and to recommend an alternative. . . . In
May of 2009 the Skagit County's Skagit Comprehensive
Flood Hazard Management Plan (CFHMP) Advisory Committee (AC) provided input on
the Skagit GI measures. This input also included locally identified
projects that will be considered for inclusion in the Comprehensive Flood Hazard
Management Plan (CFHMP). ... We encourage the Army Corps
to utilize the results of this effort in its narrowing process. . . . “One of the flood reduction measures being considered is to create additional storage in Ross Reservoir. To accomplish this outcome power generation operations would have to be modified. This concept has been under discussion for more than 20 years. There are many serious concerns about this alternative including that the current operations and flows from the project are set by the FERC License and Settlement Agreement signed by all concerned federal and state agencies and tribes. As proposed, this measure would have high impacts to federally listed Chinook salmon and high financial cost to SCL for which we would need to be compensated.” |
| Skagit County Documents | ||
| 3/1976 | Skagit River Flooding: An Overview by Skagit County Rural Development Committee |
Given what the committee had to work with in 1976 this was a pretty good attempt
at documenting the flood issue in Skagit County. However, given what we know
now it would not stand historical challenges. Such as: they rely heavily on the
Steward Report. They did not know that Stewarts Report was unfinished, or that
Mr. Stewart was dead at the time the report was published, nor the fact that Mr.
Bodhaine had never been to Skagit County. Given the fact that the entire document was printed in the SVH in weekly installments one has to wonder why no one paid any attention to what the document had to say with respect to development in the floodplain that now burdens the taxpayer with multi-millions to protect that same development. The irony is that if the dike districts and the cities and towns get their way they will be promoting even more development that in the long run will cost the taxpayers even more money. |
| 11/15/2011 | Letter to Governor Gregoire, Re: Skagit lnstream Flow Rule |
“Swinomish Chairman Cladoosby recently told the three of us that he intends to control land use in the Skagit Basin by controlling the water supply, effectively bypassing Growth Management Act (GMA) process. From our standpoint, this sentiment explains the present conflict over water rights in the Skagit Basin. ... Skagit County has prohibited most development on floodplain, farmland, and forestland, consistent with the GMA. The stream basins at issue are the same narrow swath of pre-foothill land in Skagit County identified under the GMA for limited rural growth.” |
| Skagit County Flood Control Zone District Advisory Committee Documents | ||
| 11/21/2011 | Agenda for November 21, 2001 Meeting |
Meeting will discuss Skagit River GI & Baker FERC Relicensing 107 (c). |
| 9/19/2011 |
“Baker FERC Relicensing 107 (c): “Berentson explained that the settlement agreement required a report be filed three years from the date of license that addresses imminent dam drawdown, including a means and method for doing so. The County felt it was not being adequately consulted regarding the report. As a result, meetings have been held between the County and Puget Sound Energy (PSE). The County’s concern is that not enough storage is being addressed in the analysis of storage, and has filed comments asking PSE to complete it without Water Control Manual constraints.” |
|
| Swinomish Tribal Documents | ||
| 4/9/1976 | Swinomish Tribal Community ltr to Seattle District USACE re Swinomish Channel Dredging DEIS | "Overall, however, it (Swinomish trap and drag seining catch) has exhibited more or less the same fluctuations in level of production as other local Indian fisheries (Tulalip, Samish, and Lummi) and there is no apparent relationship between catch and channel maintenance operations. " It is surprising to see a statement such as this which boldly contradicts graphed trends which you, as well as we, have on file (See Exhibits • la, lb, 1c). There is an expressed decline in both Chinook and Chum catches immediately following the 1937 jetty construction. Furthermore, these declines are local in nature deviating from ether Indian fishery trends to the immediate north and south near the mouths of neighboring rivers. . . . The only other major environmental change at this time which could have so dramatically affected the fish catch was the jetty construction in 1937. . . . It may be difficult to show statistically that dike construction diminished the number of fish because of all the variables. However, it would be even more difficult to draw the conclusion that "dike construction probably did not diminish the number of fish." Certainly, important fish habitat and access was diminished. Logically, the fact that the number of fish was diminished would be a more reasonable conclusion than that the number was not diminished by the dike construction. . . . It has always been this Tribal Community's policy to work cooperatively. To us, this means a two-way give-and-take relationship. |
| 9/7/2011 | Swinomish Tribal Community Ltr to Corps of Engineers Re: Skagit General Investigation Scoping Comments | “As we have stated from the onset, the Tribe cannot take a position regarding the acceptability of any the alternatives until adequate environmental studies are done to determine the extent, if any, to Tribal fisheries resources. Our position has been consistent in this regard, as can be observed in the letter (attached) sent to the Corps in 1963 detailing our concerns regarding the Avon Bypass. Therefore, a common concern that has not yet been adequately addressed is the lack of environmental analysis that has been undertaken to date as part of the GI study. Given the financial resources available to the Corps and time frame that you are striving to complete the study, we are concerned that the environmental analysis necessary to make informed decisions will be lacking.” |
| 11/17/2011 | Letter to Governor Chris Gregoire, Re: Skagit County Government Letter on Skagit Instream Flow Rule |
“It is a lie for the County to say that the Swinomish Tribe intends to control
off-Reservation land use in the Skagit River basin by controlling water supply,
and it is a lie to say that I told the County Commissioners any such thing.
These repeated lies can only confuse and inflame the public. So let there be no
doubt: the Swinomish Tribe does not want to control off-Reservation land use in
Skagit County. But it does want the County and Ecology to follow the law and
live up to their agreements.” See also: 11/15/2011 Letter to Governor Gregoire, Re: Skagit lnstream Flow Rule |
| Guest Documents | ||
| 6/28/2011 | US Army Corps of Engineers Trinity River Project, Dallas TX- In-Progress Review Read-Ahead | “Corps re-writing the EA [Environmental Assessment] to ensure that no language is in the document that validates design or efficacy of modification/measure being proposed. Additionally purpose and need of EA is so that the city might maintain eligibility in the National Flood Insurance Program, not provide flood risk benefits.” |
| 11/15/2011 | Property Casualty 360° - Another CR with Short-Term NFIP Extension on Horizon |
“The House and Senate are expected to pass another continuing resolution by
Friday that will keep both the federal government and the NFIP running until
Dec. 16, 2011, according to officials of the Independent Insurance Agents and
Brokers Association of America. That action will avoid any federal government or
NFIP interruptions, says Charles Symington, IIABA senior vice president of
government affairs According to State Farm, which is
exiting the Write-Your-Program because of the uncertainty in the NFIP, this will
be the 12th last-minute reauthorization of the NFIP since 2002. On four
occasions, the program was allowed to lapse for extended periods of time,
according to State Farm officials ” |
| General Webpage Updates for November 2011 | ||
| Historical Quote of the Month | A 1976 observation about basic laws of floodplain management & physics. | |
| Issues Page | New documents posted this month to Avon Bypass Issues, Baker River Dams Issues, Corps Study & Report Issues, Dredging Issue, Fish Issues, Flood History Issues, Ross Dam Issues & Skagit County Flood Control Zone District/SC FCZD Issues | |
| Links | Added a new link to FloodSmart.gov plus updated many links to their correct places. | |
| Rain Gauge |
Updating for October 2011. |
|